TLC
TLC HOURLY FEE ESTIMATE ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES NEW MAINTENANCE HANGAR C AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)
REV 1 01-13-2020
| MECH | PLUMB | FIRE PROT | ADMIN | |||||||
| Task Description | Principal | Engineer II | Engineer I | Engineer I | Engineer I | Office Admin | Total Man-Hours | Total Task Cost | Rate/Task | Phase Total |
|---|---|---|---|---|---|---|---|---|---|---|
| Task 8: Construction Administration Services | $ 4,253.84 | |||||||||
| A Pre-construction Meeting w Airport- on-site (N/A) | 0 | $ - | #DIV/0! | |||||||
| B Review RFI's/Submittals | 4 | 4 | 2 | 10 | $ 1,115.40 | 111.54 | ||||
| C Review RCO's | 4 | 4 | $ 446.16 | 111.54 | ||||||
| D Preparation of ASI's | 2 | 2 | 4 | $ 349.94 | 87.49 | |||||
| E Bi-Weekly Coordination Meetings- teleconference | 8 | 8 | $ 892.32 | 111.54 | ||||||
| F Site Meetings (2 Visits) | 8 | 8 | $ 892.32 | 111.54 | ||||||
| G Substantial punchlist | 1 | 1 | $ 111.54 | 111.54 | ||||||
| H Final punchlist | 1 | 1 | $ 111.54 | 111.54 | ||||||
| I Prepare close-out documents | 1 | 1 | 1 | 3 | $ 334.62 | 111.54 | ||||
| TOTAL MAN-HOURS | 0 | 29 | 0 | 5 | 3 | 2 | 39 | $ 4,253.84 | ||
| LABOR RATES - HOURLY | $ 188.22 | $ 111.54 | $ 95.23 | $ 111.54 | $ 111.54 | $ 63.43 | ||||
| SUB-TOTAL LABOR COSTS | $ - | $ 3,234.66 | $ - | $ 557.70 | $ 334.62 | $ 126.86 | $ - | $ 4,253.84 | ||
| REIMBURSABLE COSTS | ||||||||||
| Printing, Reproduction, Binding, Shipping, Etc. | $ - | |||||||||
| Travel Reimbursement | $ - | |||||||||
| SPECIAL SERVICES | ||||||||||
| TOTAL | $ 4,253.84 | |||||||||
Page 1 of 1