TLC HOURLY FEE ESTIMATE ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES NEW MAINTENANCE HANGAR C AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)

REV 1 01-13-2020

MECHPLUMBFIRE PROTADMIN
Task DescriptionPrincipalEngineer IIEngineer IEngineer IEngineer IOffice AdminTotal Man-HoursTotal Task CostRate/TaskPhase Total
Task 8: Construction Administration Services$ 4,253.84
A Pre-construction Meeting w Airport- on-site (N/A)0$ -#DIV/0!
B Review RFI's/Submittals44210$ 1,115.40111.54
C Review RCO's44$ 446.16111.54
D Preparation of ASI's224$ 349.9487.49
E Bi-Weekly Coordination Meetings- teleconference88$ 892.32111.54
F Site Meetings (2 Visits)88$ 892.32111.54
G Substantial punchlist11$ 111.54111.54
H Final punchlist11$ 111.54111.54
I Prepare close-out documents1113$ 334.62111.54
TOTAL MAN-HOURS029053239$ 4,253.84
LABOR RATES - HOURLY$ 188.22$ 111.54$ 95.23$ 111.54$ 111.54$ 63.43
SUB-TOTAL LABOR COSTS$ -$ 3,234.66$ -$ 557.70$ 334.62$ 126.86$ -$ 4,253.84
REIMBURSABLE COSTS
Printing, Reproduction, Binding, Shipping, Etc.$ -
Travel Reimbursement$ -
SPECIAL SERVICES
TOTAL$ 4,253.84

Page 1 of 1