HOURLY FEE ESTIMATE
ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES
NEW MAINTENANCE HANGAR C
AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)
REV 1 01-13-2020
| MECH | PLUMB | FIRE PROT | ADMIN | |
| Task Description | Principal | Engineer II | Engineer I | Engineer I | Engineer I | Office Admin | Total Man-Hours | Total Task Cost | Rate/Task | Phase Total |
|---|
| Task 8: Construction Administration Services | | | | | | | | $ 4,253.84 |
|---|
| A Pre-construction Meeting w Airport- on-site (N/A) | | | | | | | 0 | $ - | #DIV/0! |
|---|
| B Review RFI's/Submittals | | 4 | | 4 | 2 | | 10 | $ 1,115.40 | 111.54 |
|---|
| C Review RCO's | | 4 | | | | | 4 | $ 446.16 | 111.54 |
|---|
| D Preparation of ASI's | | 2 | | | | 2 | 4 | $ 349.94 | 87.49 |
|---|
| E Bi-Weekly Coordination Meetings- teleconference | | 8 | | | | | 8 | $ 892.32 | 111.54 |
|---|
| F Site Meetings (2 Visits) | | 8 | | | | | 8 | $ 892.32 | 111.54 |
|---|
| G Substantial punchlist | | 1 | | | | | 1 | $ 111.54 | 111.54 |
|---|
| H Final punchlist | | 1 | | | | | 1 | $ 111.54 | 111.54 |
|---|
| I Prepare close-out documents | | 1 | | 1 | 1 | | 3 | $ 334.62 | 111.54 |
|---|
| | | | | | | | | |
| TOTAL MAN-HOURS | 0 | 29 | 0 | 5 | 3 | 2 | 39 | | | $ 4,253.84 |
|---|
| LABOR RATES - HOURLY | $ 188.22 | $ 111.54 | $ 95.23 | $ 111.54 | $ 111.54 | $ 63.43 | | | |
|---|
| SUB-TOTAL LABOR COSTS | $ - | $ 3,234.66 | $ - | $ 557.70 | $ 334.62 | $ 126.86 | $ - | $ 4,253.84 | |
|---|
| REIMBURSABLE COSTS | | | | | | | | | |
|---|
| Printing, Reproduction, Binding, Shipping, Etc. | | | | | | | | $ - | |
|---|
| Travel Reimbursement | | | | | | | | $ - | |
|---|
| SPECIAL SERVICES | | | | | | | | | |
|---|
| TOTAL | | | | | | | | $ 4,253.84 | |
|---|