BBM STRUCTURAL ENGINEERS, INC. HOURLY FEE ESTIMATE ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES NEW MAINTENANCE HANGAR C AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)

REV 1 01-13-2020

Task Description STRUCTURAL

Principal Project Manager Project Engineer CADD Tech Const. Admin Admin Total Man-Hours Total Task Cost Rate/Task

Task 8: Construction Administration Services

A Pre-construction Meeting w Airport- on-site 0 $ - #DIV/0!

B Review RFI's/Submittals 8 32 40 $ 4,344.00 108.60

C Review RCO's 4 4 $ 420.00 105.00

D Preparation of ASI's 4 4 8 $ 812.00 101.50

E Bi-Weekly Coordination Meetings- teleconference 0 $ - #DIV/0!

F Site Meetings (1) 8 8 $ 840.00 105.00

G Substantial punchlist 0 $ - #DIV/0!

H Final punchlist 0 $ - #DIV/0!

I Prepare close-out documents 4 2 6 $ 602.00 100.33

TOTAL MAN-HOURS 0 0 8 8 50 0 66

LABOR RATES - HOURLY $ 192.00 $ 150.00 $ 123.00 $ 98.00 $ 105.00 $ 54.00

SUB-TOTAL LABOR COSTS - - $ 984.00 $ 784.00 $ 5,250.00 $ - - 7,018.00 $ 7,018.00

REIMBURSABLE COSTS

Printing, Reproduction, Binding, Shipping, Etc. $ -

Travel Reimbursement $ 300.00

SPECIAL SERVICES

TOTAL $ 7,318.00