American Infrastructure Development, Inc. HOURLY FEE ESTIMATE ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES NEW MAINTENANCE HANGAR C AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)

REV 1 01-13-2020

CIVIL
Task DescriptionPrincipalProject ManagerSenior EngineerEngineerSenior DesignerClericalTotal Man-HoursTotal Task CostRate/TaskPhase Total
Task 8: Construction Administration Services$ 28,608.00
A Coordinate with Owner and SSA1212$ 2,208.00184.00
B Pre-construction Meeting w Airport- on-site268$ 1,340.00167.50
C Review RFI's/Submittals81624$ 3,424.00142.67
D Review RCO's448$ 1,180.00147.50
E Preparation of ASI's16161648$ 6,256.00130.33
F Bi-weekly Coordination Meetings- teleconference1212$ 1,944.00162.00
G Site Meetings448$ 1,180.00147.50
H Site Visits (2x/month for 6 months)4848$ 6,384.00133.00
I Substantial punchlist44$ 648.00162.00
J Final punchlist448$ 1,180.00147.50
K Prepare close-out documents2416426$ 2,864.00110.15
TOTAL MAN-HOURS0166292324206
LABOR RATES - HOURLY$ 214.00$ 184.00$ 162.00$ 133.00$ 96.00$ 78.00
SUB-TOTAL LABOR COSTS$ -$ 2,944.00$ 10,044.00$ 12,236.00$ 3,072.00$ 312.00$ -$ 28,608.00$ 28,608.00
REIMBURSABLE COSTS
Printing, Reproduction, Binding, Shipping, Etc.
Travel Reimbursement
SPECIAL SERVICES
Landscape Architecture - CA3636$ 4,788.00133.00
Quality Assurance- Civil/Sitework (not to exceed)$ 20,000.00
TOTAL FEES - PROFESSIONAL SERVICES$ 55,546.40