American Infrastructure Development, Inc. HOURLY FEE ESTIMATE ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES NEW MAINTENANCE HANGAR C AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)
REV 1 01-13-2020
| CIVIL | ||||||||||
| Task Description | Principal | Project Manager | Senior Engineer | Engineer | Senior Designer | Clerical | Total Man-Hours | Total Task Cost | Rate/Task | Phase Total |
|---|---|---|---|---|---|---|---|---|---|---|
| Task 8: Construction Administration Services | $ 28,608.00 | |||||||||
| A Coordinate with Owner and SSA | 12 | 12 | $ 2,208.00 | 184.00 | ||||||
| B Pre-construction Meeting w Airport- on-site | 2 | 6 | 8 | $ 1,340.00 | 167.50 | |||||
| C Review RFI's/Submittals | 8 | 16 | 24 | $ 3,424.00 | 142.67 | |||||
| D Review RCO's | 4 | 4 | 8 | $ 1,180.00 | 147.50 | |||||
| E Preparation of ASI's | 16 | 16 | 16 | 48 | $ 6,256.00 | 130.33 | ||||
| F Bi-weekly Coordination Meetings- teleconference | 12 | 12 | $ 1,944.00 | 162.00 | ||||||
| G Site Meetings | 4 | 4 | 8 | $ 1,180.00 | 147.50 | |||||
| H Site Visits (2x/month for 6 months) | 48 | 48 | $ 6,384.00 | 133.00 | ||||||
| I Substantial punchlist | 4 | 4 | $ 648.00 | 162.00 | ||||||
| J Final punchlist | 4 | 4 | 8 | $ 1,180.00 | 147.50 | |||||
| K Prepare close-out documents | 2 | 4 | 16 | 4 | 26 | $ 2,864.00 | 110.15 | |||
| TOTAL MAN-HOURS | 0 | 16 | 62 | 92 | 32 | 4 | 206 | |||
| LABOR RATES - HOURLY | $ 214.00 | $ 184.00 | $ 162.00 | $ 133.00 | $ 96.00 | $ 78.00 | ||||
| SUB-TOTAL LABOR COSTS | $ - | $ 2,944.00 | $ 10,044.00 | $ 12,236.00 | $ 3,072.00 | $ 312.00 | $ - | $ 28,608.00 | $ 28,608.00 | |
| REIMBURSABLE COSTS | ||||||||||
| Printing, Reproduction, Binding, Shipping, Etc. | ||||||||||
| Travel Reimbursement | ||||||||||
| SPECIAL SERVICES | ||||||||||
| Landscape Architecture - CA | 36 | 36 | $ 4,788.00 | 133.00 | ||||||
| Quality Assurance- Civil/Sitework (not to exceed) | $ 20,000.00 | |||||||||
| TOTAL FEES - PROFESSIONAL SERVICES | $ 55,546.40 | |||||||||
Page 1 of 1