SCHENKEL SHULTZ
HOURLY FEE ESTIMATE
ADD SERVICE #4- CONSTRUCTION ADMINISTRATION SERVICES
NEW MAINTENANCE HANGAR C
AT THE SARASOTA-BRADENTON INTERNATIONAL AIRPORT (SRQ)
REV 1 01-13-2020
Task Description ARCHITECTURE
Senior Project Manager Sr. Project Manager QC/Permit Senior Project Arch Architect Cad Intermediate Sr. Interior Designer Construction Administrator Total Man-Hours Total Task Cost Rate/Task Phase Total
Task 8: Construction Administration Services $ 32,936.92
A Pre-construction Meeting w Airport- on-site 2 2 $ 238.48 119.24
B Review RFI's/Submittals 8 24 72 104 $ 13,324.16 128.12
C Review RCO's 4 16 20 $ 2,556.00 127.80
D Preparation of ASI's 12 16 28 $ 3,381.28 120.76
E Bi-Weekly Coordination Meetings- teleconference (12 total) 12 12 24 $ 3,219.36 134.14
F Site Meetings (6) 6 18 24 $ 3,054.36 127.27
G Substantial punchlist 8 16 24 $ 3,185.76 132.74
H Final punchlist 4 8 12 $ 1,592.88 132.74
I Prepare close-out documents 4 8 8 20 $ 2,384.64 119.23
TOTAL MAN-HOURS 0 0 32 40 20 0 166 256
LABOR RATES - HOURLY $ 163.26 $ 163.26 $ 138.34 $ 119.24 $ 108.52 $ 129.94 $ 129.94
SUB-TOTAL LABOR COSTS - - $ 4,426.88 $ 4,769.60 $ 2,170.40 $ - $ 21,570.04 $ - $ 32,936.92 $ 32,936.92
REIMBURSABLE COSTS
Printing, Reproduction, Binding, Shipping, Etc. $ 1,000.00
Travel Reimbursement - 6 Site Visits mileage $ 1,200.00
SPECIAL SERVICES
TOTAL $ 35,136.92
Page 1 of 1