Tierra Proposal 65-20-527
Sarasota Intl. Airport (SRQ) Proposed Rental Car, Parking and Storage Facilities
Tierra Inc Standard Fee Schedule
Item DescriptionUnitUnit PriceQuantityTotal
Geotechnical Field Investigation
612-Geo Mobilization Drill Rig Truck MountEach$ 350.002$ 700.00
418-Geo Drill Crew Support VehicleDay$ 160.004$ 640.00
Geo SPT Truck 0-50 FtLF$ 12.90320$ 4,128.00
Geo Grout Boreholes- Truck 0-050 FtLF$ 5.25320$ 1,680.00
Geo Temp Casing 3" Truck 0-050 FtLF$ 8.5080$ 680.00
401-Geo Auger Borings- Hand & Truck/Mud BugLF$ 10.50175$ 1,837.50
432-Geo Field Permeability 0-10 Ft (Open - End Borehole Method)Each$ 290.004$ 1,160.00
209-Asphalt Pavement Coring – 4" dia with Base Depth CheckEach$ 125.0018$ 2,250.00
606-Mobilization Concrete CoringEach$ 250.001$ 250.00
Geotechnical Soil Laboratory Testing
812-Soils Materials Finer than 200 Sieve (FM 1-T011)Test$ 42.0015$ 630.00
817-Soils Moisture Content Laboratory (AASHTO T 265)Test$ 10.008$ 80.00
805-Soils Corrosion Series (FM 5-550 through 5-553)Test$ 175.004$ 700.00
819-Soils Organic Content Ignition (FM 1 T-267)Test$ 42.002$ 84.00
Atterberg Limit Tests (AASHTO T-89 and T-90) CombinedTest$ 130.006$ 780.00
810-Soils California Bearing Ratio (CBR)Test$ 340.0010$ 3,400.00
Engineering and Technical Support Services
Senior Project EngineerHour$ 163.198$ 1,305.52
Geotechnical EngineerHour$ 137.3624$ 3,296.64
Engineering InternHour$ 95.0032$ 3,040.00
DesignerHour$ 96.918$ 775.28
Sr Engineering TechnicianHour$ 85.174$ 340.68
Geotechnical TechnicianHour$ 68.6524$ 1,647.60
Secretary/ClericalHour$ 78.022$ 156.04
Total Estimated Fee$ 29,561.26