Reference: Proposal for Engineering Services Fuel and QTA System Design Proposed Airport Rental Car Facility Sarasota Bradenton International Airport

  • 10% Project Design Criteria narrative related to the above in-scope design elements;
  • 20% Schematic Design package to include:
  • 40% Design Development package to include:
  • 60%, 95%, and 100% Construction Documents to include:
  • Schematic design documents illustrating the scale and relationship of the primary project engineering components in common between each of the project construction phases.
  • Preliminary options for fueling and equipment design; and
  • Initial drawings and model completed to a 20% level of completion.
  • 40% drawings
  • Preliminary specifications, and
  • Updated Project Design Criteria narrative.
  • Drawings; and

Specifications completed to the appropriate level of detail.

We have assumed that 100% documents will be sealed by a Florida Professional Engineer and that response to up to two rounds of agency comments are included.

Included in the design phase services will be one on-site meeting or site walk, and attendance at weekly design meetings and virtual design coordination meetings.

Bid Support

Stantec will support the bid process by providing responses to bidder questions and attending bidder meetings via teleconference or virtual meeting.

Construction Administration

Stantec has assumed that construction administration services are not included at this time, but could provide a proposal for those additional services at a later date.

Permitting

Stantec has assumed that all permitting will be completed by others and has not included permitting in this scope of work.

Design with community in mind