Reference: Proposal for Engineering Services
Fuel and QTA System Design
Proposed Airport Rental Car Facility
Sarasota Bradenton International Airport
10% Project Design Criteria narrative related to the above in-scope design elements;
20% Schematic Design package to include:
40% Design Development package to include:
60%, 95%, and 100% Construction Documents to include:
Schematic design documents illustrating the scale and relationship of the primary project engineering components in common between each of the project construction phases.
Preliminary options for fueling and equipment design; and
Initial drawings and model completed to a 20% level of completion.
40% drawings
Preliminary specifications, and
Updated Project Design Criteria narrative.
Drawings; and
Specifications completed to the appropriate level of detail.
We have assumed that 100% documents will be sealed by a Florida Professional Engineer and that response to up to two rounds of agency comments are included.
Included in the design phase services will be one on-site meeting or site walk, and attendance at weekly design meetings and virtual design coordination meetings.
Stantec will support the bid process by providing responses to bidder questions and attending bidder meetings via teleconference or virtual meeting.
Stantec has assumed that construction administration services are not included at this time, but could provide a proposal for those additional services at a later date.
Stantec has assumed that all permitting will be completed by others and has not included permitting in this scope of work.
Design with community in mind