B. It is assumed that Cell Lot & Future RV & Boat Storage sites will be included on the same permit applications as the CONRAC for any given permitting agency as listed in the above sections. If separate applications are for each site this can be done as additional service. The basic scope includes up to two (2) resubmittals for any given permit application during the permit review and approval process.
Programming / Pre-Design (10%) Submittal
Schematic Design (30%) Submittal
Design Development (60%) Submittal
Construction Document (95%) Submittal
100% Construction Documents and Bid / Permit Documents Submittal
○ One (1) electronic copy (Adobe .pdf), transmitted electronically
One (1) electronic copy (Adobe .pdf), transmitted electronically
DWG/C3D design files
One (1) electronic copy (Adobe .pdf), transmitted electronically
DWG/C3D design files
One (1) electronic copy (Adobe .pdf), transmitted electronically
DWG/C3D design files
One (1) electronic copy (Adobe .pdf), transmitted electronically
○ One (1) digitally signed & sealed plan set for permit submittals
○ DWG/C3D design files
The Programming / Pre-Design Documents (10%) will be completed within twelve (12) weeks of the Notice to Proceed (NTP).
The Schematic Design Documents (30%) will be completed within ten (10) weeks of the Programming / Pre-Design Submittal.
The Design Development Documents (60%) will be completed within twelve (12) weeks of the Schematic Design Submittal.
The Construction Documents (95%) will be completed within twelve (12) weeks of the Design Development Submittal.
The Bid Documents will be completed within eight (8) weeks of the Construction Documents Submittal.
The Bidding Phase Services will be completed within four (4) weeks of the Bids being advertised by SMAA CM/GC.