The Consultant will update the site/civil Design Report to document additional design progress.
The Consultant will provide quantities in order for a third-party estimator to prepare a preliminary rough order of magnitude cost estimate for the site/civil design to be included in the design report.
The Consultant shall conduct an in-house quality control review of the Construction Document Plans and Design Report prior to the submittal to PGAL in accordance with the Consultant QC Plan.
Utilizing comments from SMAA, SWFWMD, and other Authorities Having Jurisdiction, the Consultant will complete the plans and specifications to a level necessary for bidding. This will include finalizing necessary calculations, detailing, planning, etc. to complete the design process. Civil Documents will be updated to include bidding dates and requirements as provided by SMAA and provided to PGAL for inclusion in final bid documents.
It is anticipated that there will be one (1) progress review meeting with SMAA for this phase of the Project.
The Consultant will provide quantities in order for a third-party estimator to prepare a preliminary rough order of magnitude cost estimate for the site/civil design to be included in the design report.
The Consultant shall conduct an in-house quality control review of the Bid Document Plans and Design Report prior to submittal to SMAA in accordance with the Consultant QC Plan.
This task includes assistance to PGAL during the bidding phase of the Project. The Consultant will prepare for and attend the Pre-Bid Conference and address technical questions. The Consultant will also respond to written technical questions from prospective bidders which are submitted to SMAA with respect to the documents prepared under this scope of services. The Consultant will prepare addenda relating to the design as necessary to interpret or clarify the Bidding Documents for construction.
The Consultant's PM and/or appropriate technical leads shall prepare and submit the following permit applications to the respective agencies:
Generic Permit for Stormwater Discharge from Large and Small Construction Activities (NPDES NOI) – Provide technical assistance to the Contractor for submittal to Florida Department of Environmental Protection
Right of Way Utilization Permit – Provide technical assistance to the Contractor for submittal to City of Sarasota Public Works.
It is assumed the terminal's storm water management, utility systems, and central plant have the existing capacity for this expansion. New lift station design is not included with this scope. This assumption will be reviewed; however, design for improvements to these systems are excluded, as our task does not involve storm water and environmental permit reviews, engineering design, nor calculations.