The Consultant will provide quantities in order for a third-party estimator to prepare a preliminary rough order of magnitude cost estimate for the site/civil design to be included in the design report.
The Consultant will prepare a 7460 for the temporary construction and proposed site plan for the Project in accordance with FAA requirements. The Consultant will solicit input from the Airport regarding necessary safety and phasing requirements for the construction of the Project.
The Consultant shall conduct an in-house quality control review of the Design Development (60%) Plans and Design Report prior to submittal to PGAL in accordance with the Consultant QC Plan.
specifications are not available for a construction item, the Consultant will create the necessary technical specification.
Under this task, the Consultant will review the comments received from SMAA on the Design Development submittal review and incorporate applicable comments into plans, specifications, and design narrative. Then the Consultant will continue to progress the plans, specifications, and drawings to a Construction Document (95%) design level. At the Construction Document design level, the Project elements and details will be essentially complete and ready for final review. When the Construction Documents are submitted to PGAL, they shall be considered final design documents pending only SMAA review, comments, and approval to proceed with bidding.
The Consultant will assist PGAL in developing a project manual for use during the bidding and construction of this project in accordance with Federal, State, and Local requirements.
The Consultant's PM and/or appropriate technical leads will prepare for and attend approximately three (3) web-based owner optional workshop/ progress meetings and one (1) in person workshop/presentation meeting.
The Consultant’s PM and/or appropriate technical leads shall schedule, prepare responses to requests for additional information requested from City of Sarasota and/or the SFWMD relative to the information provided in the initial development application submittals. FDEP Water and Wastewater permit application will be submitted upon approval. The Consultant’s PM and/or appropriate technical leads shall prepare and submit the following permit applications to the respective agencies:
Environmental Resource Permit & Consumptive Water Use (if required for reclaim water) – Southwest Florida Water Management District (SWFWMD)
Site Plan Approval – City of Sarasota Development Review
Utility Plan Approval – City of Sarasota Utility Department
General Permit to Construct a Public Water System (PWS) Distribution System (FDEP Water Permit) – Florida Department of Environmental Protection
Notification/Application for Constructing A Domestic Wastewater Collection/Transmission System (FDEP Wastewater & Reclaim Water Permit) – Florida Department of Environmental Protection