The Consultant will provide quantities in order for a third-party estimator to prepare a preliminary rough order of magnitude cost estimate for the site/civil design to be included in the design report.
The Consultant shall conduct an in-house quality control review of the Schematic Design plans and design narrative prior to submittal to PGAL in accordance with the Consultant QC Plan.
Drawings/exhibits including overall site/civil plans
Schematic Design (30%) Site/Civil Design Report
Topographic/SUE Survey
Report on the Order of Magnitude Opinion of Probable Construction Cost for site/civil elements.
Summary of overall identified code issues and assumptions
This task includes the development of drawings and specifications necessary and appropriate for a Design Development level of design as determined by the Consultant. The Design Development drawings are intended to include major design items and provide enough information to define the scope of the Project. Major project elements will be set and considered essentially final, but detailed design items may not be included in this submission.
The Engineer shall review the comments received from SMAA from the Schematic Design submittal review and incorporate applicable comments into plans, specifications, and design narrative. The Engineer shall provide a written response to each comment stating how it will be incorporated into the documents or why it was not applicable.
The Consultant's PM and/or appropriate technical leads will prepare for and attend approximately six (6) web-based owner optional workshop/ progress meetings and two
in person workshop/presentation meeting.
The Consultant’s PM and/or appropriate technical leads shall schedule, prepare calculations, exhibits, and other supporting documents required for application submittals to the City of Sarasota and the SWFWMD. FDEP Water and Wastewater permit application will be submitted upon approval of the utility plans approval from Manatee County Utilities for Water & Wastewater and the City of Sarasota Utility Department for Reclaim Water. The Consultant’s PM and/or appropriate technical leads shall prepare and submit the following permit applications to the respective agencies:
Environmental Resource Permit & Consumptive Water Use (if required for reclaim water) – Southwest Florida Water Management District (SWFWMD)
Site Plan Approval – City of Sarasota Development Review
Utility Plan Approval – Manatee County Utilities (Water & Wastewater) City of Sarasota Utility Department (Reclaim Water)
The Consultant will develop a Design Report for the basis of design.
The Consultant will develop draft technical specifications for the Project based on the FDOT or CSI MasterFormat standards as appropriate. If standard technical