• Initial review of overall code issues and assumptions. Discuss alternative procurement methods for equipment and systems.
  • Preparation of land survey and geotechnical and environmental analysis of the proposed site(s), once the developable area has been defined in the planning / pre-design phase, and the re-platting of sites for a continuous project site for development. Environmental analysis, Phases 1 and 2, as bests to testing and reporting, monitoring well, drilling and reporting, will be included as an additional service, as needed.

Deliverables:

  • Summary of Site/Civil Project Design Criteria
  • Report on the Qualitative/Performance based “program” for primary components (sizing goals and planning parameters)
  • Summary of findings defining the scope of the project, conceptual approach and an opinion of probable construction cost

3. Schematic Design (30%)

  • Under this task the Consultant will perform planning, coordination, field work, preliminary studies and schematic plan development necessary to evaluate, align and expand previous planning work relative to Pre-Design findings with a focus on the primary aspects in common to each of the project construction phase areas. At this phase, the design will include enough of the project design components to reflect the project goals and objectives while still allowing for modifications. This phase of the design will include the development of base drawings and CAD/Civil 3D models of civil / site design. AutoCAD 2018 or newer shall be used for civil designs. The Schematic Design submittal will include the following:
  • Cover Sheet
  • Index of Drawings
  • General Notes
  • Site Plan
  • Preliminary Phasing
  • Clearing and Grubbing / Demolition Plan
  • Demolition/Site Closeout Plans of Existing Facilities
  • Typical Sections including Pavement Design
  • Paving and Geometry Plan
  • Grading and Drainage Analysis and Plan (including Stormwater Modeling)
  • Pavement Marking and Signage Plan
  • Water & Sewer Utility Plan
  • Landscape Plan
  • Remediation Plans
  • Fencing Plan
  • The Consultant's PM and/or appropriate technical leads will prepare for and attend approximately six (6) web-based owner optional workshop/ progress meetings and two (2) in person workshop/presentation meeting.
  • Perform topographical survey of the proposed site.
  • Perform underground survey utilities of the proposed site.