J. ENERGY:

  • a. Updated energy report

K. GENERAL:

  • As documents develop, confer with regulatory agencies such as:
  • Identify all documents with project number and date
  • Finalize the building design program, scope of work and verify compliance through the project quality assurance / quality control program
  • Actions for the civil, mechanical and electrical engineers:
  • Fire Marshal (state and local)
  • Department of Health
  • City and County of Sarasota
  • Local zoning commission
  • Local planning commission
  • Local permitting commission
  • Contact utility companies and public authorities for all services and initiate approval process as needed for connection to their systems
  • Investigate and report on their review of all applicable local, public and utility regulations

L. GEOTECHNICAL REPORT:

  • a. Provide a final copy of the project geotechnical report

M. ESTIMATES:

  • Major line items costs for all building components, verify inclusion of all elements by cross checking against specification for omissions
  • Identify escalation to mid-point of construction
  • Update cost estimate of construction and compare it to the allowable for construction
  • Estimate the construction period, identify any phased work and any long-lead time for special item
  • Sole source items identified as approved

N. PROJECT SCHEDULE:

11

  • a. Present Microsoft Project Schedule outlining Design Milestones and Major Construction activities