SRQ Quick Turnaround and Maintenance Facilities Sarasota Bradenton International Airport Sarasota, Florida
Revised 12.23.2020
J. ENERGY:
a. Updated energy report
K. GENERAL:
As documents develop, confer with regulatory agencies such as:
Identify all documents with project number and date
Finalize the building design program, scope of work and verify compliance through the project quality assurance / quality control program
Actions for the civil, mechanical and electrical engineers:
Fire Marshal (state and local)
Department of Health
City and County of Sarasota
Local zoning commission
Local planning commission
Local permitting commission
Contact utility companies and public authorities for all services and initiate approval process as needed for connection to their systems
Investigate and report on their review of all applicable local, public and utility regulations
L. GEOTECHNICAL REPORT:
a. Provide a final copy of the project geotechnical report
M. ESTIMATES:
Major line items costs for all building components, verify inclusion of all elements by cross checking against specification for omissions
Identify escalation to mid-point of construction
Update cost estimate of construction and compare it to the allowable for construction
Estimate the construction period, identify any phased work and any long-lead time for special item
Sole source items identified as approved
N. PROJECT SCHEDULE:
11
a. Present Microsoft Project Schedule outlining Design Milestones and Major Construction activities