- ii.Locate under slab sanitary and supply lines
- iii.Locate maintenance hose bibs in toilet rooms and on exterior of building
- iv.Include roof drainage system (quantity and location of roof drains, internal and external downspouts)
- v.Locate, specify, and indicate any seasonal systems and design accommodations
- vi.Coordinate fixture sizes and mounting heights (for accessibility)
- vii.Coordinate plumbing chases with architectural
- viii.Consider installation and replacement requirements within all room layouts
- ix.Coordinate plenum ceiling space with architectural, fire protection, mechanical, electrical, structural systems
- x.Coordinate piping size and flows for sprinklers (if applicable)
- xi.Make arrangements with the water company to have a hydrant flow test made to identify water pressure to site and include the flow test report
c. Catalog Cuts:
- i.Plumbing fixtures
- ii.Sprinkler heads and fire suppression systems (as required)
- iii.Special equipment
G. ELECTRICAL:
a. Floor Plans:
- i.Size and locate utility equipment on architectural plans
- ii.Major electrical equipment (switch gear, distribution panels, emergency generator, transfer switches, UPS system, etc.)
dimensioned and drawn to scale into the space allocated, to include riser diagrams or one-line diagrams
- iii.Finalize service amperage and voltage requirements
- iv.Locate size of conduit runs, cable trays, risers, shafts, chases, etc.
- v.Locate site electrical equipment including transformers, underground service, entrance details, etc.
- vi.Identify feature lighting fixtures: ceiling and wall types reflective ceiling plan
- vii.Locate and identify service controls and equipment for seasonal systems
- viii.Locate and Identify entry/exit circulation and/or perimeter seasonal systems, service connections and controls as necessary
- ix.Locate and identify service connection, controls and equipment associated with air curtains, area heating, radiant heating (if required)
9