• Locate under slab sanitary and supply lines
  • Locate maintenance hose bibs in toilet rooms and on exterior of building
  • Include roof drainage system (quantity and location of roof drains, internal and external downspouts)
  • Locate, specify, and indicate any seasonal systems and design accommodations
  • Coordinate fixture sizes and mounting heights (for accessibility)
  • Coordinate plumbing chases with architectural
  • Consider installation and replacement requirements within all room layouts
  • Coordinate plenum ceiling space with architectural, fire protection, mechanical, electrical, structural systems
  • Coordinate piping size and flows for sprinklers (if applicable)
  • Make arrangements with the water company to have a hydrant flow test made to identify water pressure to site and include the flow test report

c. Catalog Cuts:

  • Plumbing fixtures
  • Sprinkler heads and fire suppression systems (as required)
  • Special equipment

G. ELECTRICAL:

a. Floor Plans:

  • Size and locate utility equipment on architectural plans
  • Major electrical equipment (switch gear, distribution panels, emergency generator, transfer switches, UPS system, etc.) dimensioned and drawn to scale into the space allocated, to include riser diagrams or one-line diagrams
  • Finalize service amperage and voltage requirements
  • Locate size of conduit runs, cable trays, risers, shafts, chases, etc.
  • Locate site electrical equipment including transformers, underground service, entrance details, etc.
  • Identify feature lighting fixtures: ceiling and wall types reflective ceiling plan
  • Locate and identify service controls and equipment for seasonal systems
  • Locate and Identify entry/exit circulation and/or perimeter seasonal systems, service connections and controls as necessary
  • Locate and identify service connection, controls and equipment associated with air curtains, area heating, radiant heating (if required)