description of items to be served by emergency power and describe consideration for special areas

I. SPECIALTY CONSULTANTS:

  • Design criteria defined for QTA Fueling and other required systems (vacuum, fluids, etc.)
  • One line plans as appropriate (fuel, fluids, vacuum, etc.)
  • Provide narrative and plan layout on project wayfinding requirements
  • Provide narrative and one-line for telecommunications/data systems
  • Provide narrative and one-line for security and access control systems

J. LANDSCAPING:

  • a. Functional analysis of site program

K. OUTLINE SPECIFICATIONS:

  • a. Identify specification sections and major building material systems and finishes

L. ENERGY REPORT:

  • Life cycle cost analysis of energy conservation measures
  • Annual energy consumption/SF of building space
  • Energy analysis:
  • Comparison of energy source alternatives, including renewable energy
  • Life cycle costing for value analysis of mechanical system alternatives
  • Preliminary mechanical system sizing
  • Energy budgeting for proposed facilities

M. GEOTECHNICAL REPORT:

  • a. Provide a draft copy of the geotechnical report

N. ESTIMATES:

  • Major component cost estimate, verify inclusion of elements by cross checking against outline specification for omissions and compare with budget
  • Identify escalation factors to mid-point of construction
  • Estimate construction period, identify any phased work and any long lead time for special items
  • 4
  • Sole source items identified and justified
  • Area tabulation gross SF to net SF