2.2 Engineering Design

  • Prepare and submit for approval schematic design documents illustrating the scale and relationship of the primary project engineering components in common between each of the project construction phases.
  • Prepare and submit for approval preliminary options for all engineering disciplines, including Civil, Structural, Mechanical, Electrical, Plumbing, Fire Protection, IT/Data systems, Fueling and Equipment, and Landscape design.
  • Develop preliminary phasing and schedule alternatives and coordinate with the Owner.
  • Continue development of base drawings and CAD / Revit model of all project areas, site and buildings.

2.3 Cost Estimating & Scheduling

  • Develop preliminary phasing and schedule alternatives and coordinate with the Owner.
  • Develop an Order of Magnitude Opinion of Probable Construction Cost for the project based on area calculations.
  • Cost Management through establishment of realistic capital costs of construction. Analyze and develop the best course of action in regard to cost estimation and cost control.
  • Conduct a cost and schedule review meeting with Owner to agree on costs prior to moving into the Design Development phase.

3.0 DESIGN DEVELOPMENT – 40%

Develop design based on the approved Schematic Design, Owner authorization of any adjustments in the project requirements and budget for the cost of the work for project construction based on Schematic Design. The 40% Design documents shall illustrate and describe the refinement of the design of the project to establish the scope, relationships, functionality, forms, size and performance of the project by means of plans, sections, typical construction details and equipment layouts.

The 40% Design documents shall consist of drawings and other documents, including specifications, to fix and describe the size and character and establish their quality level of the project scope of work. The documents shall demonstrate the coordination of the site and building design amongst architectural, civil, landscape, structural, mechanical, electrical, plumbing, fire protection, specialty systems, fueling and equipment, as well as other work that may be required for construction of the project.

Meetings

The Designer will conduct, as needed and as required, approximately six (6) web-based owner optional workshop/progress meetings and two (2) in person workshop/presentation meetings.

Deliverables

  • 40% DD drawings consisting of 1/8" plans, sections, elevations, enlarged floor plans, design details, preliminary schedules, single line diagrams, outline material specifications, written scope of work narrative, draft project phasing plans, draft engineering reports, draft construction material sample boards for finishes and code required drawings in electronic PDF format to the Owner.
  • Report on the 40% design construction cost estimate in electronic PDF format to the Owner.
  • Printed copies, if requested by Owner.