operation providing exclusive-use areas for each rental car company (3 in total). A preferred option will be reviewed and selected during the initial phase of the project by project stakeholders.
Included in this work is the development of the overall site and surrounding roadways, drainage, utilities, lighting, and signage.
Demolition of the existing QTA sites (Hertz, Enterprise and Storage Lot), including all vertical facilities, buildings, fuel tanks, and any site improvements, to be returned to a rough graded site. Environmental site investigation, asbestos and soils testing is included and provided by the Design Team. Any site or building remediation, if needed, will be by others.