operation providing exclusive-use areas for each rental car company (3 in total). A preferred option will be reviewed and selected during the initial phase of the project by project stakeholders.

EXHIBIT 3 – PROPOSED QTA OPERATIONS – SEMI-SECURED

EXHIBIT 4 – PROPOSED QTA OPERATIONS – SECURED

  • Included in this work is the development of the overall site and surrounding roadways, drainage, utilities, lighting, and signage.
  • Demolition of the existing QTA sites (Hertz, Enterprise and Storage Lot), including all vertical facilities, buildings, fuel tanks, and any site improvements, to be returned to a rough graded site. Environmental site investigation, asbestos and soils testing is included and provided by the Design Team. Any site or building remediation, if needed, will be by others.