Sarasota Manatee Airport Authority Sarasota Bradenton International Airport – Rehabilitate Taxiways C and F
Coordinate with Southwest Florida Water Management District (SWFWMD) via meeting on the project impacts. It is anticipated that the project impacts will be minimal and no SWFWMD permit will be required. Permitting, if required, will be completed as an additional service.
Deliverables:
Documentation from outcome of coordination with SWFWMD.
5. Video Inspection of Storm Drain Pipes
Level of Service:
Complete video inspection of existing storm drainage pipes under Taxiway C. Existing length of pipe to be inspected is estimated to be 4500 linear feet (10 crossings), as depicted on attached figure. Pipe inspection will require subcontractor to complete minimal plugging and dewatering pipes (assumes completion in dry season), followed by light cleaning (desilting) and inspection. Video inspection data will be evaluated based on the data from the data provided by the pipe lining or other repair. If needed, design for pipe lining or other repair will be completed as an additional service.
Deliverables:
Results of video inspection in suitable electronic format and memo documenting pipe condition and recommendations.
Part III - Excluded Services
Wetland identification, delineations, mapping, permitting, mitigation design.
Endangered species surveys.
Environmental Assessments beyond categorical exclusion evaluation.
Stormwater drainage modifications or environmental resource permitting.
Hazardous materials studies or assistance.
Construction phase services.