Sarasota Manatee Airport Authority Sarasota Bradenton International Airport – Rehabilitate Taxiways C and F
The preliminary construction plans will be submitted to the Airport, FAA and FDOT for review and comment. Comments will be incorporated into the final design construction plans.
Deliverables:
Electronic PDF versions of the preliminary construction plans will be submitted to the Airport, FAA and FDOT for review and comment. Comments will be incorporated into the final design/bidding documents.
3. Project Manual and Specifications
Level of Service:
The project manual and specifications will be prepared using the standard specifications of FAA Advisory Circular 150/5370-10, latest change, adapted to the project including all FAA and/or FDOT approved deviations to standards.
During this phase, the project manual and specifications document will be revised and updated to approximately a 60% level. The sections and provision are not final and will require further refinement during the final design stage.
Deliverables:
Electronic PDF versions of the project manual and specifications document will be submitted to the Airport, FAA and FDOT for review and comment. Comments will be incorporated into the final design/bidding documents.
4. Conduct a Quality Assurance Review
Level of Service
The design team shall conduct a technical and plan sheet coordination review before submittal of the preliminary design deliverables items.
Deliverables:
Electronic PDF versions of the meeting note comments and markup notes will be submitted to the Airport.
5. Engineer's Report
Level of Service:
Prepare the draft of the Engineer's Report for the project. The report will discuss design criteria, specific design solutions, modifications to standards, copies of design calculations, construction time and cost estimates, and information used to estimate liquidated damages.
Deliverables:
Electronic PDF versions of the engineer report will be submitted to the Airport, FAA and FDOT.
6. Preliminary (60%) Design Review Meeting
Level of Service
The design team shall participate in a design review with Airport staff to review the 60% design plans and documents.
Deliverables:
Electronic PDF versions of the meeting note comments will be submitted to the Airport.
Final Design
1. Project Management
5