Project Fee Proposal - TLC Engineering Solutions
Sarsoslu Brudenton Airport
Rental Car Facility Quick Turn Around and Maintenance Area - Add Service No. 1 - Garage
7/13/2021
Design PhasesDirectorProject ManagerSr. Mech EngMech Eng IIMech Eng IFP EngPlumbing EngSr. Elect EngElect Eng IIElect Eng ISr. TechnologyTech DesignerAdministrativeTotal
Task Description
1Task 1 - Programming (20%)
2Coordination of team activities, scheduling, and project comm822442426
3Utility and infrastructure review and recommendations44412
4Basis of Design Document22228
5Project Management2810
6
Task 1 - Subtotal Hours2.0016.00---2.002.0010.004.002.008.0010.00-56
Subtotal Direct Labor (- 420.38 $ 3,177.44 $ - - - - - $247.12 $ 203.92 $ 1,985.90 $ 494.24 $ 203.92 $ 1,636.00 $ 982.90 $ - - 9,351.82
7 Task 2 - Schematic Design (40%) (8 weeks)
8 Design Meetings (x6)44412
9 IGAAC Meetings (x2)2226
10 Code analysis62210
11 Calculations442414
12 Design Concepts Validation - Narrative0
13 SMAA Page flip442212
14 Coordination48242424
15 Quality Control2222210
16 Response to teams QA/QC Comments22228
17 Project Management224
18 Task 2 - Subtotal Hours2.0010.00----22.0020.0018.008.00-16.004.00-100
Subtotal Direct Labor (- 420.38 $ 1,985.90 $ - - - - 2,718.32 $ 2,039.20 $ 3,574.62 $ 988.48 $ - - 3,272.00 $ 393.16 $ - - 15,392.06
19 Task 3 - Design Development (60%) (12 weeks)28
20 Weekly OAC Meetings44444440
21 Weekly OAC Meetings14
22 Coordination22222248
23 Drawing Development8848480
24 Specification Development12
25 SMAA Page flip4222216
26 Quality Control222222212
27 Response to teams QA/QC Comments8224412
28 Project Management2810
29 Cell Phone Lot0
30 Task 3 - Subtotal Hours2.0018.00----20.0020.0014.0020.0012.0014.0020.00-140
Subtotal Direct Labor (- 420.38 $ 3,574.62 $ - - - - 2,471.20 $ 2,039.20 $ 2,780.26 $ 2,471.20 $ 1,223.52 $ 2,863.00 $ 1,965.80 - - $ 19,809.18
31 Task 4 - Construction Documents (90%) (8 weeks)444424
32 Weekly Design Meetings24
33 Weekly OAC Meetings0
34 Coordination222222214
35 Drawing Development884884848
36 Specification Development224416
37 Energy Model16
38 SMAA Page flip42814
39 Quality Control2222218
40 Response to Comments222222212
41 Project Management246
42 Task 4 - Subtotal Hours2.0014.00----22.0016.0016.0020.0012.0024.0020.006.00152
Subtotal Direct Labor (- 420.38 $ 2,780.26 $ - - - - 2,718.32 $ 1,631.36 $ 1,177.44 $ 2,471.20 $ 1,223.52 $ 4,908.00 $ 1,965.80 $ 516.66 $ 21,812.94
43 Task 5 - Bid and Permit Documents (100%) (6 weeks)2222214
44 Bid REIT's44444420
45 Plan Review submission222222214
46 Response to Comments2222220
47 Task 5 - Subtotal Hours-4.00----8.008.008.006.00-4.004.006.0048
Subtotal Direct Labor (- 794.36 - - - - $ 988.48 $ 815.68 $ 1,588.72 $ 741.36 - - $ 818.00 $ 393.16 $ 516.66 $ 6,656.42
48 Task 6 - Construction Administration0
49 Submittal Review0
50 Field Observation0
51 Response to Questions/Coordination0
52 Meetings/Management0
53 Review Change Order Proposals0
54 Issue Modifications to Documents0
55 Punchlist/Witness Testing0
56 Record Drawings0
57 Project Management0
58 Task 6 - Subtotal Hours--------------0
Subtotal Direct Labor (- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

TOTAL FEE S 73,022.42

/