SRQ Rental Car Quick Turnaround Area and Surrounding Projects Sarasota Bradenton International Airport

Exhibit C2 - Fee Proposal - Team Synopsis - GARAGE ADDITION

9/13/2021

Firms and Disciplines Project Phases Other Services Subtotals % of Overall Fee

10% Design 30% SD 60% DD 95% CD 100% CD Bid/Permit CA

PGAL

Project Management - 5,550 $ 7,400 $ 3,700 $ 1,850 na $ 18,500 4.80%

Rental Car Planning - 4,890 $ 6,520 $ 3,260 $ 1,630 na $ 16,300 4.23%

Architecture and Interiors - 47,610 $ 63,480 $ 31,740 $ 15,870 na $ 158,700 41.16%

Masters Consulting Engineers (see attached breakdown of fees)

Structural Engineering - 23,093 $ 44,058 $ 22,029 $ 7,343 na $ 96,523 25.04%

Stantec

Fueling and Systems Engineering - - - - - na - 0.00%

Atkins North America

Civil Engineering - - - - - na - 0.00%

Site Topographic SUE and Survey na - - 0.00%

Landscape Architecture - - - - - na - 0.00%

ESA - Phases 1 and 2 ( to be provided as needed as a contract amendment) $ - 0.00%

TLC Engineering Solutions (see attached breakdown of fees)

M / E/ P / FP / IT $ 9,352 $ 15,392 $ 19,809 $ 21,813 $ 6,656 na $ 73,022 18.94%

Tierra

Asbestos Demolition Survey and Screening (to be completed by separate contractor, per discussions with SMAA) $ - 0.00%

Geotechnical Engineering - difference between original scope/fee ($29,562) and new fully defined scope, previously approved $ - 0.00%

Jensen Hughes

Code Report for Garage Addition (ROM, NTE amount) $ 22,500 5.84%

Reimbursable Expenses

Estimate, based on approximately 3.0% of overall fee $ - 0.00%

Totals $ 9,352 $ 96,535 $ 141,267 $ 82,542 $ 33,349 $ - $ 22,500 385,545 100.00%

Notes: Construction Costs Fee %

1 Fee proposal includes full design services as outlined in the detailed scope of work and design deliverables $ 15,000,000 2.57%

$ 20,000,000 1.93%

$ 25,000,000 1.54%