Mr. Kent Bontrager, C.M., P.E. Sarasota Manatee Airport Authority Consolidated RAC QTA and Maintenance Facilities at SRQ – Additional Services Request September 13, 2021 Page 2 of 2

Precast Garage Architectural Model

Other changes to our original and contracted scope includes the addition of the cell phone lot to a site located south of Rental Car Road and the removal of any design or engineering work for the existing Hertz lot. Work planned for Parcel 2 for parking is not part of our scope but will be coordinated with our design efforts through SMAA.

This request will follow the same design and submission requirements as outlined in our contract, including Exhibit A – Detailed Scope of Services, Exhibit B – Design Deliverables, and Exhibit E – Project Schedule. The attached Exhibit C2 identifies fee request and detailed back-up, in the overall contract amendment change order amount of $385,545, or approximately 2% of anticipated construction costs.

Please let me know if you have any questions or comments regarding this request, and if additional information is needed. We look forward to commencing with this work as we move into our design development phase of the project.

Sincerely,

effrey A. Weiner, AlA executive Vice President

CC: Payal Harrell, Accounting – PGAL