Bid and Award
Project Fee Proposal - C&S Team - Summary Sheet
SRQ GA FIS Facility
SRQ SMAA Project Number: XXX
April-21
Scope/Task SOM DM ME CE SPE PE Eng S. Designer Designer PA SAD ID AD Total
Basic Design Services Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours
Part 1 - Bid & Award - C&S
General
C&S shall assist SRQ in advertising for and obtaining bids for the contract for construction, materials, equipment and services. 1 1
Receive and respond as required to questions from potential bidders regarding the Contract Documents. 7 2 6 6 21
Attend pre-bid conference that is scheduled and conducted by SMAA-SRQ and advise SMAA-SRQ on matters relating to design. 12 8 20
Prepare ad-sends to the bid documents after advertisement and prior to bidding as required upon the SMAA's approval. 5 1 6 4 2 2 2 12 34
Prepare bid tribution sheets. 2 2
Perform bid reviews. 2 2
Assist SMAA-SRQ in evaluating bids or proposals and in assembling and awarding contracts for construction, materials, equipment, and services. C&S will review bids and proposals and any relevant market conditions related to such bids, and provide a written evaluation thereof, including a detailed analysis of bids potentially subject to award which may appear to be unseasonably higher or lower than the recommended estimate (when 2 2
Provide a recommendation to award C&S shall note in the evaluation any irregularities, deviations, qualifications, or conditions set forth in such bids or 2 2
Subtotal Hours - 33.00 3.00 12.00 10.00 2.00 - 2.00 - 2.00 - - 20.00 84
Rate $ 89.30 $ 70.10 $ 58.50 $ 45.00 $ 34.00 $ 29.00 $ 30.00 $ 30.00
Subtotal Direct Labor - 2.313.30 $ 165.00 $ 50.30 $ 90.00 $ 61.00 $ 127.00 $ 600.00
Subtotal Burdened Labor @ 2.89 - 6.685.44 $ 476.85 $ 2.028.78 $ 1.453.67 $ 260.10 $ 176.29 $ 176.29