100% Construction Documents
Project Fee Proposal - C&S Team - Summary Sheet
SRQ GA FIS Facility
SRQ SMAA Project Number: XXX
April-21
Scope/TaskSGMDMMECESPEPEEngS. DesignerDesignerPASADIDADTotal
Basic Design ServicesHoursHoursHoursHoursHoursHoursHoursHoursHoursHoursHoursHoursHours
Part I - 100% Construction Documents - C&S
Task 40Prepare 100% Contract Drawings incorporating all design aspects of the project and surrounding site.17264620225481640
Task 41Prepare 100% Specifications9112348
Task 42Develop calculations packages including - Structural Calculations - Energy Calculations - Hydraulic Calculations64184840
Task 43Develop detailed quantity takeoffs of all bid items to refine opinion of cost.42212
Task 50Finalize opinion of probable construction costs for each major element of the Project.6414
Task 51Perform final internal quality control review on all designs documents.1094224
Task 52Attend a final review meeting with SRQ to discuss and resolve final comments.9122
Task 53Review and develop written responses to all comments received.627222
Task 54Submit to all AHP's required per the permit schedule for permitting.44
Subtotal Hours10.0070.0012.00109.0021.0022.0032.0054.00-24.00-16.0052.00422
Rate$ 89.30$ 70.10$ 55.00$ 58.50$ 50.30$ 45.00$ 34.00$ 30.50$ 29.00$ 63.50$ 38.00$ 30.00$ 30.00
Subtotal Direct Labor$ 893.00$ 4907.00$ 660.00$ 6376.50$ 1056.30$ 990.00$ 1088.00$ 1647.00$ -$ 1524.00$ -$ 480.00$ 1560.00$ 21,181.80
Subtotal Burdened Labor @1.89$ 2580.77$14,181.23$ 1,907.40$ 18,428.09$ 3052.71$ 2861.10$ 3,144.32$ 4,759.83$ -$ 4,404.36$ -$ 1,387.20$ 4,508.40