90% Construction Documents

Project Fee Proposal - C&S Team - Summary Sheet

SRQ GA FIS Facility

SRQ SMAA Project Number: XXX

April-21

Scope/Task SGM DM ME CE SPE PE Eng S. Designer Designer PA SAD ID AD Total

Basic Design Services Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours

Part I - 90% Construction Documents - C&S

Task 3 REMOVED

Task 30 Prepare 90% Contract Drawings and Specifications incorporating all design aspects of the project and surrounding site to clearly describe the construction requirements for bidding and execution. This work will include dimensioning and definition of plans, sections, elevations, and details, as well as schedules to define the work. 21 8 96 10 56 48 132 32 24 160 587

Task 36 Review, Coordinate, and finalize front end specifications for bid package. 12 12

Task 37 Finalize technical specifications manual for bid package. 15 2 24 4 12 40 97

Task 38 Perform internal quality control review on all design documents. 12 85 1 4 2 2 8 38

Task 40 Pre-application forms and requirements will be developed in preparation for permitting. 4 4

Task 41 Finalize development and evaluation of construction schedule. 4 4

Task 42 REMOVED 0

Task 43 REMOVED 0

Task 39 Permit schedule will be finalized for the items to be submitted and anticipated review times. 3 3

Task 44 Setup and attend one (1) design review meeting with SRQ, CBP, and other stakeholders. 13 4 3 2 2 24

Task 45 Review and develop written responses to all comments received. 7 12 2 2 8 31

Subtotal Hours 12.00 87.30 11.00 140.00 21.00 58.00 48.00 132.00 - 56.00 - 24.00 210.00 799.5

Rate $ 89.30 $ 70.10 $ 55.00 $ 58.50 $ 50.30 $ 45.00 $ 34.00 $ 30.50 $ 29.00 $ 63.50 $ 38.00 $ 30.00 $ 30.00

Subtotal Direct Labor $ 1,071.60 $ 6,133.75 $ 605.00 $ 8,190.00 $ 1,056.30 $ 2,610.00 $ 1,632.00 $ 4,026.00 - 3,556.00 - 720.00 $ 6,300.00 $ 35,900.65

Subtotal Dotted Labor 2.89 $ 3,096.92 $17,726.54 $ 1,748.45 $ 23,669.10 $ 3,052.71 $ 7,542.90 $ 4,716.48 $11,635.14 -10,276.84 - 2,080.80 $ 18,207.00 $103,752.88