Schematic Design

Project Fee Proposal - C&S Team - Summary Sheet

SRQ GA FIS Facility

Scope/Task SGM DM ME CE SPE FE Eng S. Designer Designer PA SAD ID AD Total

April-21

SRQ SMAA Project Number: XXX

Basic Design Services Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours

Part 1 - Schematic Design - C&S

Task 12 REMOVED

Task 13 Schedule coordination - consultant shall provide continued coordination so that project schedules are met for each phase of work included in this contract. Particular phases of design may be delayed by the FAA and FDOT review process. 2 2

Task 14 Our team will engage other permitting agencies to begin the coordination process and sharing the preliminary documents and permitting objectives. 2 8 2 12

Task 15 Update Concept Design Report based on selections decisions made and comments received during review. 9 12 3 4 8 36

Task 16 Prepare Schematic Drawings (30's) incorporating all design aspects of the project and scromsfing site. 32 8 83 18 28 40 100 8 48 40 120 530

Task 17 Perform internal quality control review on all design documents. 3 5 2 2 8 23

Task 18 Develop an outline of front end and technical specifications. 2 1 2 1 4 10

Task 19 Preliminary development and examination of construction schedule. 9 8

Task 20 Perform a preliminary quantity takeoff of all bid items. 2 8 4 4 18

Task 21 Prepare preliminary opinion of probable construction costs for each major element of the Project. 3 3 2 4 6 25

Task 22 Setup and attend one (1) design review meeting with SRO, CBP, and other stakeholders. 13 4 3 2 2 24

Task 23 Review and develop written responses to all comments received. 8 12 2 2 4 28

Subtotal Hours 800 88.00 11.00 144.00 31.00 28.00 48.00 100.00 8.00 70.00 - 40.00 142.00 718

Rate $ 59.30 $ 70.10 $ 55.00 $ 58.50 $ 50.30 $ 45.00 $ 34.00 $ 30.50 $ 29.00 $ 63.50 $ 38.00 $ 30.00 $ 30.00

Subtotal Direct Labor $ 714.40 $ 6168.80 $ 603.00 $ 8,424.00 $ 1,559.30 $ 1,260.00 $ 1,632.00 $ 3,050.00 $ 232.00 $ 4,445.00 - 1,200.00 $ 4,260.00 $ 33,550.50

Subtotal B昭新 Labor @ 289 $ 2,064.62 $17,827.83 $ 1,748.43 $ 24,345.36 $ 4,506.38 $ 3,641.40 $ 4,716.48 $ 8,814.50 $ 670.48 $12,846.05 - 3,468.00 $12,311.40 $ 96,960.93