Programming/Concept Design

Project Fee Proposal - C&S Team - Summary Sheet

SRQ GA FIS Facility

SRQ SMAA Project Number: XXX

April 21

Scope/Task PM S Eng CS SPE GE EI SS SET GI Designer Clinical CEIA Total

Basic Design Services Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours

Part 1 - Project Definition - Tierra Geotechnical

Perform 6 hand augers to a depth of 5 feet below existing ground and two (2) California Bearing Ratio tests in the area of the proposed parking lot. 2 8 6 1 17

Perform four (4) Standard Penetration Tests to a depth of 25 feet below the existing ground surface in the area of proposed structure. 2 2 1 5

Perform soil classifications for all borings performed including as needed laboratory verification testing. 2 6 8

Draft the boring profiles. 4 4

Summarize all testing in a geotechnical report signed and sealed by a FL PE 2 6 8 16

Subtotal Hours - 2.00 - 8.00 - 18.00 - 10.00 6.00 6.00 - - 50

Subtotal Direct Labor - 150.74 - 523.04 - 622.44 - 340.00 $ 163.26 $ 250.50 - -

Subtotal Burdened Labor @ 3.00 - 452.22 - 1,569.12 - 1,867.32 - 1,020.00 $ 489.78 $ 751.50 - -

Rate $ 72.25 $ 75.37 $ 57.96 $ 65.38 $ 52.50 $ 34.58 $ 46.91 $ 34.00 $ 27.21 $ 41.75 $ 41.93 $ 20.00