Programming/Concept Design

Project Fee Proposal - C&S Team - Summary Sheet

SRQ GA FIS Facility

SRQ SMAA Project Number: XXX

April-21

Scope/Task CE SET Total

Basic Design Services Hours Hours

Part I - Project Definition - Hough Engineering Inc

Identify applicable permit and code requirements and enforcing government agencies 2 2 4

Permit schedule will be created for the items to be submitted and anticipated review times. 2 t 3

Subtotal Hours 4.00 3.00 7

Rate $ 220.00 $ 140.00

Subtotal Direct Labor $ 830.00 $ 420.00 $ 1,300.00

Subtotal Burdened Labor @ 1.00 $ 830.00 $ 420.00 $ 1,300.00