EXHIBIT A FEE ESTIMATE
Project Fee Proposal - C&S Team - Summary Sheet
SRQ GA FIS Facility
SRQ/SMAA Project Number: XXX
April-21
Basic Design Services Concept 30% 60% 90% 100% Total Bid & Total W/MBE % % W/MBE % Construction
Engineering & Preconstruction Services Design Schematic Design Dev. Const. Does Final Docs Design Award of Design Fee Goal Cost
C&S $ 68,139.55 $ 96,960.95 $ 114,890.94 $ 103,752.88 $ 61,215.40 $ 444,959.72 $ 13,182.16 $ 458,141.87
Hough $ 1,300.00 $ 1,300.00 $ 1,440.00 $ 1,300.00 $ 720.00 $ 6,060.00 $ 6,060.00
Hyatt $ 8,049.51 $ 8,049.51 $ 8,049.51 5.35% 3.00%
Tierra $ 6,149.94 $ 6,149.94 $ 6,149.94
Design Phase Sub Total $ 83,639.01 $ 98,260.95 $ 116,330.94 $ 105,052.88 $ 61,935.40 $ 465,219.17 $ 13,182.16 $ 478,401.33
Travel / Hotel / Meals - Charrettes $ 2,313.00 $ 224.00 $ 223.00 $ 2,313.00 $ 5,073.00 $ 5,073.00
Monthly Travel $ 224.00 $ 224.00 $ 223.00 $ 223.00 $ 223.00 $ 1,117.00 $ 1,117.00
Parking $ 40.00 $ 40.00 $ 40.00 $ 40.00 $ 40.00 $ 200.00 $ 200.00
Tierra
Materials / Testing $ 5,984.00 $ 5,984.00 $ 5,984.00
Total Fee, Allowances, Reimbursable Expenses $ 92,200.01 $ 93,748.95 $ 116,816.94 $ 107,628.88 $ 62,198.40 $ 477,593.17 $ 13,182.16 $ 490,775.33
Reimbursable Expenses
C&S
Sub Total $ 8,561.00 $ 488.00 $ 486.00 $ 2,576.00 $ 263.00 $ 12,374.00 - 12,374.00
Allowances