| Charrette 4 | Jan 2022 | • Kickoff Construction Documents Phase | • Updated Goals/Objectives list • Updated Action Items list |
|---|
| 90 % Construction Documents | 2.5 months | • Permit-level construction documents, inclusive of details, specifications, and applicable calculations • Substantial Completion Opinion of Cost | • 90% CD Drawings • Substantially complete front end and technical specifications • Updated Opinion of Cost • Written responses to all comments received |
|---|
| Airport/CBP Review | 2 weeks | • Review 90% Construction Documents | |
|---|
| 100 % Construction Documents | 1 month | • Final construction documents, inclusive of comments after final review • Final Opinion of Cost | • Permit (100% CD) Drawings • Finalized front end and technical specifications • Finalized Opinion of Cost • Written responses to all comments received |
|---|
| Airport/CBP Review | 1 week | • Review 100% Construction Documents | |
|---|
| Permitting | 4-6 weeks* | • Respond to permit comments | • Submit drawings electronically |
|---|
| Bidding & Award | 2 months | • Prepare Bid Package • Advertise Bid | • Bid Package |
|---|