SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
Charrette 4Jan 2022• Kickoff Construction Documents Phase• Updated Goals/Objectives list • Updated Action Items list
90 % Construction Documents2.5 months• Permit-level construction documents, inclusive of details, specifications, and applicable calculations • Substantial Completion Opinion of Cost• 90% CD Drawings • Substantially complete front end and technical specifications • Updated Opinion of Cost • Written responses to all comments received
Airport/CBP Review2 weeks• Review 90% Construction Documents
100 % Construction Documents1 month• Final construction documents, inclusive of comments after final review • Final Opinion of Cost• Permit (100% CD) Drawings • Finalized front end and technical specifications • Finalized Opinion of Cost • Written responses to all comments received
Airport/CBP Review1 week• Review 100% Construction Documents
Permitting4-6 weeks*• Respond to permit comments• Submit drawings electronically
Bidding & Award2 months• Prepare Bid Package • Advertise Bid• Bid Package
*Dependent on AHJ review process. Typically this takes and average of ± 30 days