E. ANTICIPATED SCHEDULE & DELIVERABLES

C&S will approach the project in the key phases tabulated below. C&S acknowledges the importance of the Project Schedule to SRQ and CBP and agrees to put forth reasonable efforts in performing the services under this proposal with due diligence in a manner consistent with the durations listed below. SRQ agrees that C&S' performance must be governed by sound professional practices. The Project Schedule shall be equitably adjusted as the project progresses, allowing for changes in scope caused by unknown conditions, character or size of the project as verbally requested or in-writing by SRQ/SMAA/CBP and/or for delays or other causes beyond C&S' reasonable control.

PHASEDURATIONSERVICESDELIVERABLES
AwardJuly 2021Notice to Proceed
Charrette 1July 2021Kickoff Concept Design PhaseGoals/Objectives listAction Items list
Programming / Concept Phase6 weeksGeotechnical and SurveyProgram Definition/DevelopmentDesign ReportConceptual rendered floor planConceptual Interiors renderingsColors and finishes boards
Airport/CBP Review2 weeksReview Concept Design Documents
Charrette 2Sept 2021Kickoff Schematic Design PhaseUpdated Goals/Objectives listUpdated Action Items list
Schematic Design Phase6 weeksSchematic floorplans and site plansCode compliance and life safety informationUtility connection plansSD DrawingsOutline of front end and technical specificationsPreliminary Opinion of CostFinalized Design ReportWritten responses to all comments received
Airport/CBP Review2 weeksReview Schematic Design Documents
Charrette 3Nov 2021Kickoff Design Development PhaseUpdated Goals/Objectives listUpdated Action Items list
Design Development2 monthsDevelopment-level design plansFinalize layout of facilityIdentification of major infrastructure locations and sizesPreliminary foundation/framing loading informationDD DrawingsPreliminary front end and technical specificationsUpdated Opinion of CostWritten responses to all comments received
Airport/CBP Review2 weeksReview Design Development Documents