C&S will approach the project in the key phases tabulated below. C&S acknowledges the importance of the Project Schedule to SRQ and CBP and agrees to put forth reasonable efforts in performing the services under this proposal with due diligence in a manner consistent with the durations listed below. SRQ agrees that C&S' performance must be governed by sound professional practices. The Project Schedule shall be equitably adjusted as the project progresses, allowing for changes in scope caused by unknown conditions, character or size of the project as verbally requested or in-writing by SRQ/SMAA/CBP and/or for delays or other causes beyond C&S' reasonable control.
| PHASE | DURATION | SERVICES | DELIVERABLES |
|---|
| Award | July 2021 | Notice to Proceed | |
|---|
| Charrette 1 | July 2021 | Kickoff Concept Design Phase | Goals/Objectives listAction Items list |
|---|
| Programming / Concept Phase | 6 weeks | Geotechnical and SurveyProgram Definition/Development | Design ReportConceptual rendered floor planConceptual Interiors renderingsColors and finishes boards |
|---|
| Airport/CBP Review | 2 weeks | Review Concept Design Documents | |
|---|
| Charrette 2 | Sept 2021 | Kickoff Schematic Design Phase | Updated Goals/Objectives listUpdated Action Items list |
|---|
| Schematic Design Phase | 6 weeks | Schematic floorplans and site plansCode compliance and life safety informationUtility connection plans | SD DrawingsOutline of front end and technical specificationsPreliminary Opinion of CostFinalized Design ReportWritten responses to all comments received |
|---|
| Airport/CBP Review | 2 weeks | Review Schematic Design Documents | |
|---|
| Charrette 3 | Nov 2021 | Kickoff Design Development Phase | Updated Goals/Objectives listUpdated Action Items list |
|---|
| Design Development | 2 months | Development-level design plansFinalize layout of facilityIdentification of major infrastructure locations and sizesPreliminary foundation/framing loading information | DD DrawingsPreliminary front end and technical specificationsUpdated Opinion of CostWritten responses to all comments received |
|---|
| Airport/CBP Review | 2 weeks | Review Design Development Documents | |
|---|