SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
TASK 49
Develop detailed quantity takeoffs of all bid items to refine opinion of cost.
DELIVERABLE
Final Quantity Takeoff
TASK 50
Finalize opinion of probable construction costs for each major element of the Project.
DELIVERABLE
Opinion of Probably Construction Cost
TASK 51
Perform final internal quality control review on all design documents.
DELIVERABLE
QA/QC documents can be submitted to SRQ upon request
TASK 52
Attend a final review meeting with SRQ to discuss and resolve final comments.
DELIVERABLE
Meeting Minutes
TASK 53
Review and develop written responses to all comments received
DELIVERABLE
Responses on Drawings and Specifications in PDF form
TASK 54
Submit to all AHJ's required per the permit schedule for permitting.
DELIVERABLE
Permit Drawings and Specifications in PDF format