SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
Construction Documents Phase (100%)
The services included under this Phase fine-tune the 90% Contract Documents for the final development of the construction documents bid package for the Project, including Final Plans, Specifications, and opinion of cost. The specific services to be provided or furnished for this Phase of the Project are the following:
TASK 46
Prepare 100% Contract Drawings incorporating all design aspects of the project and surrounding site.
DELIVERABLE
Construction Drawings (100%)
SUBTASKS:
Perform project management duties such as project planning, invoice preparation, and coordination of design team.
Finalize three-dimensional (BIM) design of all elements of the project.
All design disciplines to develop and finalize all necessary sections, details, schedules, quantities, and specifications required for final development of bid package and opinion of cost.
TasK 47
Prepare 100% Specifications
DELIVERABLE
Specifications
TasK 48
Develop calculations packages including:
Structural Calculations
Energy Calculations
Hydraulic Calculations
DELIVERABLE
Calculations Package