- Finalize coordination with other disciplines
- Finalize plumbing fixture selections with architect and owner
- Provide installation details for plumbing fixtures and equipment
- Finalize equipment selections/capacities, and coordinate power requirements with electrical engineer
- Finalize routing of pipe mains throughout the facility and coordinate with other MEP infrastructure
- Route branch piping to all fixtures throughout the facility
- Finalize technical specifications, and incorporate equipment/fixture schedules into plans
- Review constructability and location of piping specialties for access/maintenance
Mechanical
- Finalize HVAC equipment and capacities based on final facility layout
- Finalize equipment layout in mechanical rooms, on rooftops, and on exterior of facility as necessary
- Finalize ductwork routing and sizes
- Finalize mechanical pipe routing and sizes
- Finalize diffuser and return locations coordinated with ceiling plan and wall layout
- Finalize project specific details
- Finalize mechanical schedules based on equipment selections
- Finalize energy calculations to be submitted with final design documents
Fire Protection
- Finalize equipment layout, sizes, and locations.
- Finalize hydraulic calculations.