SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
Finalize three-dimensional design in order to finalize pavement centerline profiles, typical sections, and other grading details for the proposed work.
Detail and finalize pavement details, rehabilitation details and pavement sections.
Finalize drainage designs and layouts and detail pipe and drainage structure installations.
Finalize water design layouts and detailing.
Finalize electrical design layouts and detailing.
Finalize fiber design layouts and detailing.
Finalize sewer design layouts and detailing.
Finalize SWFWMD permit documentation.
Finalize airfield lighting and signage.
Finalize pavement jointing.
Finalize pavement marking layouts, and detail installations.
Finalize CSPP and include in Specifications and on the Contract Drawings.
Prepare soil erosion control plan and stormwater pollution control plan and submit required documents to comply with soil erosion stormwater permit requirements for construction projects.
Architectural
Finalize Written Program and compliance with GAFDG.
Finalize building floor plans, building sections, and elevations.
Finalize construction details.
Finalize wall-types end required fire and/or acoustical ratings.
Finalize Code Compliance Plan.
Finalize exterior materials, color schedule, and wall sections.
Finalize Interior materials and color schedule
Finalize fixture, furniture, and equipment layout.