TASK 27

Develop preliminary technical specifications for each trade

DELIVERABLE

  • Preliminary Technical Specifications

TASK 28

Perform internal quality control review on all design documents.

DELIVERABLE

  • QA/QC documents can be submitted to SRQ upon request

TASK 29

Update Preliminary development and evaluation of construction schedule.

DELIVERABLE

  • Updated Preliminary Construction Schedule

TASK 30

Refine preliminary quantity takeoffs of bid items to further develop opinion of cost.

DELIVERABLE

  • Updated Preliminary Quantity Takeoff

TASK 31

Update preliminary opinion of probable construction costs for each major element of the Project.

DELIVERABLE

  • Updated Preliminary Opinion of Probably Construction Cost

TASK 32

Setup and attend one (1) design review meeting with SRQ, CBP, and other stakeholders.

DELIVERABLE

  • Meeting Minutes

TASK 33