SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
TASK 27
Develop preliminary technical specifications for each trade
DELIVERABLE
Preliminary Technical Specifications
TASK 28
Perform internal quality control review on all design documents.
DELIVERABLE
QA/QC documents can be submitted to SRQ upon request
TASK 29
Update Preliminary development and evaluation of construction schedule.
DELIVERABLE
Updated Preliminary Construction Schedule
TASK 30
Refine preliminary quantity takeoffs of bid items to further develop opinion of cost.
DELIVERABLE
Updated Preliminary Quantity Takeoff
TASK 31
Update preliminary opinion of probable construction costs for each major element of the Project.
DELIVERABLE
Updated Preliminary Opinion of Probably Construction Cost
TASK 32
Setup and attend one (1) design review meeting with SRQ, CBP, and other stakeholders.
DELIVERABLE
Meeting Minutes
TASK 33