basins, manholes, and culverts.

  1. Updated draft CSPP based on design progress.
  2. Develop a draft storm water pollution prevention plan.
  3. Prepare preliminary Contract Drawings (approximately 60% complete) providing sufficient detail for review of design concepts by SRQ, CBP, and FDOT.
  4. Develop technical specifications expected to be required for the proposed work.
  5. C&S Team shall submit information to SRQ for both the construction safety phasing plan and 7460 form so they can submit electronically to the FAA.

Architectural

  1. Conform to Written Program and GAFDG.
  2. Further develop building floor plans, building sections and elevations with general dimensions to provide scale and proportions.
  3. Define typical construction details.
  4. Define wall-types to define required fire and/or acoustical ratings.
  5. Finalize Code Compliance Plan.
  6. Develop exterior materials, color schedule, and wall sections.
  7. Develop Interior materials and color schedule.
  8. Define fixture, furniture, and equipment layout.
  9. Define door and window schedules.
  10. Refine Code Review based on any floor plan modifications since previous phase.

Structural

  1. Finalize system types and location of major structural framing.
  2. Finalize loading scheme for overall layout of facility