- Further develop three-dimensional (BIM) design models.
- Perform internal constructability review.
- Design Team shall coordinate between design discipline leads, other design team members, and airport for phasing to incorporate into drawings.
Civil
- Finalize horizontal pavement geometrical layouts and place sufficient information on drawings to layout proposed pavements in field during construction.
- Develop preliminary three-dimensional design in order to develop pavement centerline profiles, typical sections, and other grading details for the proposed work.
- Finalize pavement designs for both the parking lot and taxiway and apron which includes a HMA and PCC pavement section.
- Develop preliminary drainage designs, including computation of surface water runoff volumes, and layout facilities necessary to accommodate expected flows..
- Develop water design concept.
- Develop electrical design concept.
- Develop fiber design concept.
- Develop sewer design concept.
- Develop SWFWMD permit documentation including stormwater routing models, and other necessary documentation. At the end of this phase, an environmental resource permit (ERP) application will be submitted to SWFWMD.
- Develop preliminary parking marking layouts and continue finalization of the airfield marking layouts.
- Develop preliminary jointing plans for the PCC and HMA pavement sections.
- Continue refinement of the airfield lighting and signage layouts and detailing.
- Develop preliminary designs of structural Project elements, such as catch