1. Further develop three-dimensional (BIM) design models.
  2. Perform internal constructability review.
  3. Design Team shall coordinate between design discipline leads, other design team members, and airport for phasing to incorporate into drawings.

Civil

  1. Finalize horizontal pavement geometrical layouts and place sufficient information on drawings to layout proposed pavements in field during construction.
  2. Develop preliminary three-dimensional design in order to develop pavement centerline profiles, typical sections, and other grading details for the proposed work.
  3. Finalize pavement designs for both the parking lot and taxiway and apron which includes a HMA and PCC pavement section.
  4. Develop preliminary drainage designs, including computation of surface water runoff volumes, and layout facilities necessary to accommodate expected flows..
  5. Develop water design concept.
  6. Develop electrical design concept.
  7. Develop fiber design concept.
  8. Develop sewer design concept.
  9. Develop SWFWMD permit documentation including stormwater routing models, and other necessary documentation. At the end of this phase, an environmental resource permit (ERP) application will be submitted to SWFWMD.
  10. Develop preliminary parking marking layouts and continue finalization of the airfield marking layouts.
  11. Develop preliminary jointing plans for the PCC and HMA pavement sections.
  12. Continue refinement of the airfield lighting and signage layouts and detailing.
  13. Develop preliminary designs of structural Project elements, such as catch