- Develop preliminary size of major structural framing members
- Coordinate critical clearance requirements with architectural and MEP systems
Plumbing
- Work with the architect to develop the appropriate plumbing fixture count
- Review plumbing-specific requirements related to CBP room data sheets
- Review building type, occupancy, and perform overall code analysis related to plumbing systems
- Calculate fixture units and rationalize flow rates
- Translate overall fixture units/flow rates into pipe sizes for utility mains
Mechanical
- Perform load calculations and outdoor air ventilation calculations for proposed layout
- Develop preliminary sizes for HVAC equipment based on load calculations
- Provide preliminary selections for necessary HVAC equipment including:
- a.Air handling equipment (roof top or ground mounted).
- b.Exhaust fans
- c.Wall/roof openings (if required)
- Incorporate preliminary selections, locations, and schedules for the above equipment into drawings
- Coordinate roof openings, clearances, and/or chase requirements with the Architectural/Structural team
- Coordinate electrical load of equipment with Electrical Engineering team
- Initial main duct runs & diffuser/grille layout will be developed in accordance with the floor plan layout