Schematic Design Phase (30%)

The Schematic Design Phase is intended to further define the selections made during the Programming/Concept Phase. The design will begin to incorporate the cost-effective and practical solutions identified and the overall results will be incorporated in the 30% Schematic Drawings as a part of this phase for review by all stakeholders.

The specific services to be provided or furnished for this Phase of the Project are the following:

TASK 11

REMOVED

TASK 12

Schedule coordination - consultant shall provide continued coordination so that project schedules are met for each phase of work included in this contract. Particular phases of design may be delayed by the FAA and FDOT review process.

DELIVERABLE

  • Updated Written Schedule

TASK 13

Our team will engage other permitting agencies to begin the coordination process and sharing the preliminary documents and permitting objectives.

DELIVERABLE

  • Meeting Minutes

TASK 14

Update Concept Design Report based on selections/decisions made and comments received during review.

DELIVERABLE

  • Updated Design Report to SRQ for record

TASK 15

Prepare Schematic Drawings (30%) incorporating all design aspects of the project and surrounding site.