- 5. Summarize all testing in a geotechnical report signed and sealed by a FL PE.
TASK 6
Permit schedule will be created for the items to be submitted and anticipated review times.
DELIVERABLE
TASK 7
Develop report form, written document, depicting conceptual project options including narrative and sketch recommendations made during this phase for implementation within the overall design.
DELIVERABLE
- Submit sufficient copies of Design Report to SRQ for review and comment
SUBTASKS:
- Perform project management duties such as project planning, invoice preparation, and coordination of design team.
- Acquire and review record documents (such as plans, specifications, reports, and studies) to become familiar with data that is available for the Project.
- Identify applicable permit and code requirements and enforcing government agencies.
- Coordinate with SRQ and CBP for Program Verification.
- Begin developing three-dimensional (BIM) design models.
Civil
- 1. Assess condition of existing airfield electrical through visual site verification and interviews with SRQ staff familiar with such systems.
2. Develop concept designs
- a.Prepare one plan displaying schematic designs.
- b.Preliminary pavement horizontal geometric layouts for both the taxiway