SRQ GENERAL AVIATION FIS FACILITY SARASOTA MANATEE AIRPORT AUTHORITY
5. Summarize all testing in a geotechnical report signed and sealed by a FL PE.
TASK 6
Permit schedule will be created for the items to be submitted and anticipated review times.
DELIVERABLE
Permit Schedule
TASK 7
Develop report form, written document, depicting conceptual project options including narrative and sketch recommendations made during this phase for implementation within the overall design.
DELIVERABLE
Submit sufficient copies of Design Report to SRQ for review and comment
SUBTASKS:
Perform project management duties such as project planning, invoice preparation, and coordination of design team.
Acquire and review record documents (such as plans, specifications, reports, and studies) to become familiar with data that is available for the Project.
Identify applicable permit and code requirements and enforcing government agencies.
Coordinate with SRQ and CBP for Program Verification.
Begin developing three-dimensional (BIM) design models.
Civil
1. Assess condition of existing airfield electrical through visual site verification and interviews with SRQ staff familiar with such systems.
2. Develop concept designs
Prepare one plan displaying schematic designs.
Preliminary pavement horizontal geometric layouts for both the taxiway