| Project Fee Proposal - Hyatt Survey - Fee Detail Sheet | |||||||||
| Ground Loading Terminal Expansion | |||||||||
| Sarasota Bradenton International Airport | |||||||||
| 6/4/2021 | |||||||||
| Scope/Task | Principle / PSM | Sr. Project Manager / PSM | PSM / Project Manager | Survey Technician / CADD | Admin | 2 Man Survey Crew | 3 Man Survey Crew | Total | |
|---|---|---|---|---|---|---|---|---|---|
| Surveying & Mapping: HYATT SURVEY SERVICES | Hours | Hours | Hours | Hours | Hours | Hours | Hours | ||
| Task 1 - Topographic Survey | |||||||||
| 1.1 Topographic Survey within survey limits: | 0 | 1 | 4 | 32 | 1 | 32 | 0 | 70 | |
| 0 | |||||||||
| Subtotal Hours | - | 1.00 | 4.00 | 32.00 | 1.00 | 32.00 | - | 70 | |
| Rate | $ 256.70 | $ 207.25 | $ 146.02 | $ 113.89 | $ 45.56 | $ 148.82 | $ 184.76 | ||
| Subtotal Direct Labor | $ - | $ 207.25 | $ 584.08 | $ 3,644.48 | $ 45.56 | $ 4,762.24 | $ - | $ 9,243.61 | |
| Subtotal Burdened Labor @ | 0.00 | $ - | |||||||
| Project Fee Proposal - Hyatt Survey - Fee Detail Sheet | |||||||||
| SRQ Commercial Apron Expansion | |||||||||
| Sarasota Bradenton International Airport | |||||||||
| 6/11/2021 | |||||||||
| Scope/Task | Principle / PSM | Sr. Project Manager / PSM | PSM / Project Manager | Survey Technician / CADD | Admin | 2 Man Survey Crew | 3 Man Survey Crew | Total | |
|---|---|---|---|---|---|---|---|---|---|
| Surveying & Mapping: HYATT SURVEY SERVICES | Hours | Hours | Hours | Hours | Hours | Hours | Hours | ||
| Task 1 - Topographic Survey | |||||||||
| 1.1 Topographic Survey within survey limits: | 0 | 1 | 6 | 60 | 1 | 80 | 0 | 148 | |
| 0 | |||||||||
| Subtotal Hours | - | 1.00 | 6.00 | 60.00 | 1.00 | 80.00 | - | 148 | |
| Rate | $ 256.70 | $ 207.25 | $ 146.02 | $ 113.89 | $ 45.56 | $ 148.82 | $ 184.76 | ||
| Subtotal Direct Labor | $ - | $ 207.25 | $ 876.12 | $ 6,833.40 | $ 45.56 | $ 11,905.60 | $ - | $ 19,867.93 | |
| Subtotal Burdened Labor @ | 0.00 | $ - | |||||||
| Project Fee Proposal - Hyatt Survey - Fee Detail Sheet | |||||||||
| Apron Expansion | |||||||||
| Sarasota Bradenton International Airport | |||||||||
| 6/4/2021 | |||||||||
| Scope/Task | Principle / PSM | Sr. Project Manager / PSM | PSM / Project Manager | Survey Technician / CADD | Admin | 2 Man Survey Crew | 3 Man Survey Crew | Total | |
|---|---|---|---|---|---|---|---|---|---|
| Surveying & Mapping: HYATT SURVEY SERVICES | Hours | Hours | Hours | Hours | Hours | Hours | Hours | ||
| Task 1 - Topographic Survey | |||||||||
| 1.1 Topographic Survey within survey limits: | 0 | 1 | 3 | 16 | 1 | 24 | 0 | 45 | |
| 0 | |||||||||
| Subtotal Hours | - | 1.00 | 3.00 | 16.00 | 1.00 | 24.00 | - | 45 | |
| Rate | $ 256.70 | $ 207.25 | $ 146.02 | $ 113.89 | $ 45.56 | $ 148.82 | $ 184.76 | ||
| Subtotal Direct Labor | $ - | $ 207.25 | $ 438.06 | $ 1,822.24 | $ 45.56 | $ 3,571.68 | $ - | $ 6,084.79 | |
| Subtotal Burdened Labor @ | 0.00 | $ - | |||||||