FEE SUMMARY
PEE SUMMAR
Sarasota Bradenton International Airport
Commercial Apron Expansion/Taxiway R5 Relocation
Design, Permitting & Bidding Services
| Task | Task Description | Fee | Total Hours | Project Manager | Chief Engineer | Senior Engineer | Senior Engineer - KHA | Engineer | Admin - KHA | Designer | Admin | EOR/ Electrical | EOR/ Structural |
|---|
| $250 | $250 | $170 | $202 | $135 | $74 | $105 | $97 | $250 | $250 |
| 4 | Water Management Design and Environmental Resource Permitting | $45,940 | 254 | 24 | 40 | 150 | | 8 | | 32 | | | |
| 5 | Direct Expenses: Printing and Reproduction | $2,000 | | | | | | | | | | | |
| Sub Total: | $96,251 | 254 | 24 | 40 | 150 | 0 | 8 | 0 | 32 | 0 | 0 | 0 |
| TOTAL FEE | $420,609 | 2,073 | 318 | 165 | 158 | 175 | 710 | 44 | 168 | 86 | 174 | 75 |