| Task | Task Description | Fee | Total Hours | Project Manager | Chief Engineer | Senior Engineer | Senior Engineer - KHA | Engineer | Admin - KHA | Designer | Admin | EOR/ Electrical | EOR/ Structural |
|---|
| | | | $250 | $250 | $170 | $202 | $135 | $74 | $105 | $97 | $250 | $250 |
| PCC Jointing Details | $809 | 5 | 0 | 0 | 0 | 2 | 3 | 0 | 0 | 0 | 0 | 0 |
| Paving Elevation Plans | $3,642 | 24 | 0 | 0 | 0 | 6 | 18 | 0 | 0 | 0 | 0 | 0 |
| Pavement Sections | $674 | 4 | 0 | 0 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | 0 |
| Cross Sections | $1,215 | 9 | 0 | 0 | 0 | 0 | 9 | 0 | 0 | 0 | 0 | 0 |
| Grading and Drainage Plans | $3,470 | 24 | 0 | 2 | 0 | 0 | 22 | 0 | 0 | 0 | 0 | 0 |
| Drainage Profiles | $2,119 | 13 | 0 | 2 | 0 | 2 | 9 | 0 | 0 | 0 | 0 | 0 |
| Grading and Drainage Details | $1,579 | 9 | 0 | 2 | 0 | 2 | 5 | 0 | 0 | 0 | 0 | 0 |
| Drainage Structure Details | $4,350 | 22 | 0 | 1 | 0 | 0 | 10 | 0 | 0 | 0 | 11 | 0 |
| Pavement Marking Plans | $2,427 | 15 | 0 | 0 | 0 | 6 | 9 | 0 | 0 | 0 | 0 | 0 |
| Pavement Marking Details | $1,281 | 8 | 0 | 0 | 0 | 3 | 5 | 0 | 0 | 0 | 0 | 0 |
| General Notes - Airfield Electrical | $770 | 4 | 0 | 0 | 0 | 0 | 2 | 0 | 0 | 0 | 2 | 0 |
| Airfield Signage Modifications | $1,425 | 8 | 0 | 0 | 0 | 0 | 5 | 0 | 0 | 0 | 3 | 0 |
| Airfield Signage Details | $1,425 | 8 | 0 | 0 | 0 | 0 | 5 | 0 | 0 | 0 | 3 | 0 |
| Airfield Electrical Abbrev/Legend | $635 | 3 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 2 | 0 |
| Airfield Electrical Demolition Plans | $3,930 | 24 | 0 | 0 | 0 | 0 | 18 | 0 | 0 | 0 | 6 | 0 |
| Airfield Electrical Lighting Plans | $3,930 | 24 | 0 | 0 | 0 | 0 | 18 | 0 | 0 | 0 | 6 | 0 |
| Airfield Electrical Details | $1,965 | 12 | 0 | 0 | 0 | 0 | 9 | 0 | 0 | 0 | 3 | 0 |
| One Line Diagrams | $2,175 | 11 | 0 | 0 | 0 | 0 | 5 | 0 | 0 | 0 | 6 | 0 |
| 3.2 | Project Manual and Specifications | $5,625 | 30 | 5 | 0 | 0 | 0 | 3 | 0 | 0 | 10 | 6 | 6 |
| 3.3 | Modifications to Standards | $3,470 | 20 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 10 | 0 | 0 |
| 3.4 | Construction Safety and Phasing Plan (CSPP) | $5,007 | 27 | 10 | 0 | 0 | 6 | 6 | 0 | 0 | 5 | 0 | 0 |
| 3.5 | Opinion of Probable Construction Costs | $8,519 | 56 | 2 | 0 | 0 | 11 | 14 | 0 | 22 | 1 | 3 | 3 |
| 3.6 | Design Review/Predesign Meeting | $944 | 5 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 0 | 0 |
| 3.7 | Engineers Report | $2,500 | 10 | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Sub-Total: $120,882 | 684 | 102 | 45 | 0 | 76 | 273 | 16 | 55 | 28 | 63 | 26 |
| TASK 4 - BIDDING |
| 4.1 | Pre-Bid Meeting | $5,388 | 24 | 16 | | | | | | | 4 | 2 | 2 |
| 4.2 | Addenda Packages and Clarification Letters | $12,216 | 60 | 16 | 4 | 8 | | 8 | | | 8 | 8 | 8 |
| 4.3 | Bid Opening, Bid Tab & Recommendation of Award | $1,194 | 6 | 4 | | | | | | | 2 | | |
| Sub-Total: $18,798 | 90 | 36 | 4 | 8 | 0 | 8 | 0 | 0 | 14 | 10 | 10 |
| OTHER SERVICES |
| 1 | Design Surveys (Hyatt): | $29,111 | | | | | | | | | | | |
| 2 | Design Geotechnical Exploration (Colliers): | $19,200 | | | | | | | | | | | |
| 3 | Planning Coordination | $- | 0 | | | | | | | | | | |
Sarasota Bradenton International Airport
Commercial Apron Expansion/Taxiway R5 Relocation
Design, Permitting & Bidding Services