FEE SUMMARY Sarasota Bradenton International Airport Commercial Apron Expansion/Taxiway R5 Relocation Design, Permitting & Bidding Services

TaskTask DescriptionFeeTotal HoursProject ManagerChief EngineerSenior EngineerSenior Engineer - KHAEngineerAdmin - KHADesignerAdminEOR/ ElectricalEOR/ Structural
$250$250$170$202$135$74$105$97$250$250
General Notes - Airfield Electrical$ 1,04060000400020
Airfield Signage Modifications$ 1,945110000700040
Airfield Signage Details$ 1,945110000700040
Airfield Electrical Abbrev/Legend$ 77040000200020
Airfield Electrical Demolition Plans$ 5,6453500002700080
Airfield Electrical Lighting Plans$ 5,6453500002700080
Airfield Electrical Details$ 2,8901800001400040
One Line Diagrams$ 2,945150000700080
2.2Project Manual and Specifications$ 7,7834270005001488
2.3Modifications to Standards$ 4,85828140000001400
2.4Construction Safety and Phasing Plan (CSPP)$ 7,14539140081000700
2.5Opinion of Probable Construction Costs$ 12,898854001720034244
2.6Design Review/Predesign Meeting$ 1,63895000000400
2.7Engineers Report$ 3,5001414000000000
Sub-Total:$ 176,6311004152720994172477418537
TASK 3 - FINAL DESIGN
3.1Construction Plans$ 24,6841106232000160000
Cover Sheet$ 45040000103000
Project Drawing List$ 1,304100002206000
Summary of Quantities$ 3,58529000018011000
Abbreviations/Legend$ 48040000202000
Contract Layout Plan$ 48040000202000
Airspace Surface Protection Plan$ 87650003200000
Phasing Plans$ 2,427150006900000
Maintenance of Traffic Plans$ 2,427150006900000
Boring Log and Pvmt. Cores$ 46030100002000
Subsurface Utility Data$ 46030100002000
Existing Conditions/Survey$ 1,21480002600000
Erosion and Sed. Control Plan$ 81550200003000
Erosion and Sed. Control Details$ 71040200002000
Site Demolition Plans$ 6,0712900039000611
Site Demolition Details$ 3,539150002100066
Geometry and Paving Plans$ 3,2372100061500000
PCC Pavement Jointing Plans$ 3,7772500061900000